I think you miss understood my question.
Automated Patch Deployment for Tests.
Friday after the 2nd Tuesday of the month. Deploy patches to Test Group.
Automated Patch Deployment for entire Company.
Friday after the 3rd Tuesday of the month. Deploy patches to all Sites.
Seeing that 2nd Tuesday of the month is Microsoft's patch
deployment date. The weekend after it should be used to TEST the
patches. Then the week after we had a chance to verify the integrity
we deploy to the company.
Our current process of deploying.
Every 2nd Friday deploy to Test Group.
Every 3rd Friday deploy to all Sites.
These have had issues as there won't be any new patches on
months where the 2nd Tuesday lands
AFTER the 2nd Friday. Thus patches are 1 month behind.
Just trying to get the Automated process more perfected so we have
less manual work.